Civil Engineering

NCS have an extensive track record of civil engineering works such as reinforced concrete structures, groundworks and pile caps, retaining walls, large diameter and deep drainage, temporary works installations, marine works and other specialist or complex requirements.

Clive Street Slope Stabilisation

  • Client:

    North Tyneside Council
  • Value:

    £940,000
  • Duration:

    40 weeks

This challenging project involved the stabilisation of a 120m long sloping embankment which had slipped in the central section. To prevent further slippage, it was necessary to install a total of 637 soil nails at 20m in length to the entire slope.

View more

These were installed using long reach excavators and drilling equipment with access being necessary by use of cherry pickers due to the height of the slope. A 3 metre high temporary stone platform had to be installed along the adjacent road to act as access and safe working platform for the workforce and mechanical plant and equipment. The client imposed a restriction that the existing public highway had to remain open at all times to minimise disruption to existing apartments and businesses. This was achieved by a carefully designed traffic management system using three way traffic lights.

Once the soil nails were installed, the slope was landscaped with a selection of pioneering shrubs and wildflower grass seed, existing footpaths and stone walls were dismantled and reinstated with imported fill and topsoil. The existing stone from the walls, which was of historic interest, was reused to refurbish disused steps at one end of the site, which reinstated stepped access to the top of the embankment including ornate balustrade and handrails.

The works were completed timeously, within the Clients budget and with minimum disruption to surrounding residents and businesses.

Cobalt Business Park

  • Client:

    Highbridge Properties
  • Value:

    £2.7million
  • Duration:

    52 weeks

Cobalt Business Park is a major commercial development owned by Highbridge Properties, and NCS have been responsible for a number of infrastructure packages on the site connected with a number of new multi storey office blocks.

View more

The works have generally comprised the construction of reinforced concrete foundations, ground floor slabs, intermediate floor slabs, plant room floor screeds, foul and surface water drainage and service installations, extensive external works including road accesses, car parking areas, and hard and soft landscaping.

The works also required the installation of deep surface water attenuation systems. A combination of plastic crate systems and corrugated steel culverts together with flow regulator chambers were employed. The installation process utilised a combination of open cut and sheet pile cofferdam solutions to suit the varying ground conditions and site access restrictions. The drainage ranged in size from 100mm to 300mm in diameter and was installed to depths of up to 4metres.

The works were carried out on a very busy site which required careful planning and organisation in order to maintain trade continuity and also to suit site access provisions. All our operations were completed on time, within the Client’s budget and with minimum disruption to the normal operations of the neighbouring businesses on the Business Park.

Shed E, PD Ports Hartlepool

  • Client:

    Carillion / JDR Cables
  • Value:

    £1.4 million
  • Duration:

    21 weeks

NCs were responsible for the civil engineering works for a new production facility at the Port of Hartlepool for the production of undersea cables for the renewable and oil & gas markets.

View more

NCS’ scope of works consisted of constructing two 27m diameter by 1.2m high reinforced concrete carousels, seven complex reinforced concrete pits of different sizes and shapes up to 25m in length and up to 4.5m deep, three reinforced concrete machine base plinths, drainage works, substation and plant room foundations and plinths for prefabricated office buildings.

All works were undertaken inside an existing 200m x 50m steel clad shed which required air extraction equipment to maintain a safe working environment. Due to the nearby tidal waters, it was necessary to use dewatering equipment 24/7 to maintain safe working conditions during construction of the deep pits excavations.

A close working relationship with our client and liaison with other contractors working onsite enabled NCS to successfully accommodate late design changes and an accelerated programme to meet fixed equipment delivery dates, with phased handovers to achieve the overall required construction period.

North Shields Ferry Landing Jetty & Pontoon

  • Client:

    Nexus
  • Value:

    £150,000
  • Duration:

    11 weeks

This project involved removing corroded steel struts and beams, replacing them with new and heavier sections and installing cathodic protection. Also involved was the strengthening of 300mm x 300mm timber struts with 25mm thick steel plates, and replacing rubbing strips at the mooring timbers with heavy duty rubber rollers.

View more

The project also involved removing the anti-slip waterproofing from the jetty pedestrian walkway, and replacing it without disrupting ferry’s passengers.

The work was carried out within a tidal range of almost 5m, however working hours were restricted to minimise any hindrance to the residents living immediately adjacent to the landing jetty. NCS planned the works so that operations followed the water level down and back up again. All materials were delivered daily, by water, on the pontoon and lifted into position by chain hoists.

The final operation was to dredge the river bed below the Ferry’s pontoon, by means of an airlift.

NCS worked closely with the Client, resulting in the project being completed within budget, on time, without any safety incidents and with no disruption to the Ferry’s operations or its passengers.

Find out more

If you'd like to know more about NCS or you have a project to discuss, we'd love to hear from you - please give us a call or drop us a line.